Page 39 - H2AIR® Arch
P. 39

®
               H2AIR  ARCH


               Initial Startup Procedures

               Install Spray Nozzles & Verify Proper Function of Top Assembly and Airis®
                 5)  In  each  Top  Manifold  Assembly  install  four  (4)  of  the  supplied  Spray  Nozzles  into  the  Check
                     Bodies, refer to the image below.

                      Note:  Lubricate the Nozzle threads with a Liquid-Teflon™ for easier installation and maintenance.

























                        Top Manifold (2)                                         Check Bodies
                                                                                 Four (4) per Top Manifold


                                    Apply Liquid Teflon™ to the         Spray Nozzle
                                   Nozzle Threads at Installation       Four (4) Nozzles per Manifold
                                                                        Eight (8) Nozzles in Top Assembly

                 6)  Rotate each Spray Nozzle so it is installed at a 5° angle to the centerline of the Manifold. Be sure
                     to rotate all of the nozzles in the same direction, see the image below.






















                                                                                   5°
                                                                                     Centerline of
                                                                                     Manifold