Page 34 - H2AIR® Arch
P. 34
®
H2AIR ARCH
Utilities
Electrical Connections: Main Power for Leg Assembly LEDs
1) Remove the cover on the Electrical Box on the driver side of the Top Flip Weldment, shown
below.
Eletrical Box
Cover
Cord Grip
LED Wires for
Leg Assemblies
Top Flip Weldment
CAUTION
It is recommended that a licensed electrician is contracted to perform all electrical installations.
2) Route the Main Power Line, for the Leg Assemblies LEDs, from the Controller to the top of
H2AIR® and through the Cord Grip in the Electrical Box, shown above.
3) When everything is wired properly, close and seal the Electrical Box be cautious to not crimp
down on any of the wires.
4) Test to see if the LEDs in the Leg Assemblies are functioning properly by using the Controller to
turn on the LEDs.
30 Belanger, Inc.® *PO BOX 5470 *Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL958