Page 34 - H2AIR® Arch
P. 34

®
                H2AIR  ARCH


                Utilities

                Electrical Connections: Main Power for Leg Assembly LEDs
                    1)  Remove the cover on the Electrical Box on the driver side of the Top Flip Weldment, shown
                        below.






                      Eletrical Box
                          Cover

                        Cord Grip

                     LED Wires for
                    Leg Assemblies





                  Top Flip Weldment










                                                    CAUTION

                        It is recommended that a licensed electrician is contracted to perform all electrical installations.

                    2)  Route the Main Power Line, for the Leg Assemblies LEDs, from the Controller to the top of
                        H2AIR® and through the Cord Grip in the Electrical Box, shown above.
                    3)  When everything is wired properly, close and seal the Electrical Box be cautious to not crimp
                        down on any of the wires.
                    4)  Test to see if  the LEDs in the Leg Assemblies are functioning properly by using the Controller to
                        turn on the LEDs.























                   30     Belanger, Inc.® *PO BOX 5470 *Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681       1MANUL958
   29   30   31   32   33   34   35   36   37   38   39