             Installation


             Titan Pump Station Pressure Gauge Installation

                 The pump station has the option of mounting the Pressure Gauge on either side allowing easier access to
                 it once secured to the floor. Be sure you keep this in mind when deciding where to permanently place it.

                    1)  Determine which of the ports is best suited for your location and locate the supplied Pressure
                       Gauge.
                    2)  Secure the Gauge into place and plug the other side with the supplied plug.
                                                                                     Plugged
                                                    Gauge in                           Port
                                                     Place
                      Gauge
                       Port






             Titan Pump Station Electrical Connections

                3Phase wiring
                 Pump station requires two, 3phase connections:
                    •   3HP priming pump
                    •   10HP booster pump.
                 Each of the two motors requires 3 conductors and ground.

                 3 phase junction box, 3HP
                                                                             3 phase junction box, 10HP