Page 15 - Boss Projects Group Submission - Leidos Mezzanine Refit
P. 15

Handover

               A week prior to Practical completion Boss will begin a progressive defects and outstanding works close
               out list. This will enable our subcontracts to progressively rectify defects prior to practical completion.

               Subcontractors will finalise marked up as-installed drawings for the preparation of Final As-Installed
               drawings, Warranties and O&M Manuals. The drawings and manuals will be due for the subcontractors 2
               weeks after practical completion. Subcontractors will be required to submit to Boss prior to handover all
               Certificates of Compliances and Final Inspection reports in preparation for the final inspection to be
               performed by the Project Private Certifier.
               A handover meeting and inspection by all project stakeholders will be coordinated by Boss prior to
               Practical Completion.


               Progress Reports and Project Control Group Meetings


               Boss will ensure that progress reports are submitted. We will ensure that we contact, arrange and chair
               weekly PCG meetings to ensure that all stakeholders are kept up to date on the delivery of any project.
               We also use these PCG meeting to communicate and external consultants needs into the project inclusive
               of engineers.

               We hold regular Subcontractor Coordination meeting on all of our projects to ensure that items discussed
               in Stakeholder PCG meetings are communicated to all subcontractors.

               Our approach in Delivering the Services on Time

               Our project team has the required skill set for this project, and we able to deliver this fit out in the
               proposed  time  frame  included  in  the  tender  documents.  In  addition, our  company  has a  large  sub-
               contractor database we can call upon if required for additional support.

               Our dedicated project managers run each project in accordance with our company’ operating procedures
               and methodologies.  Our project managers are company inducted and are also familiar in the company’s
               WHSE policies and practices.

               Boss will carefully consider any project risk & provide value management to ensure successful delivery
               through Cost Management Strategies.

               Stakeholders and Principal

               Upon award of the contract, Boss Projects Group will arrange for an initial start-up meeting with the
               client representative and key team members and review all the key topics and required outcomes for
               the project. The meeting will allow all parties to review the project, program, material selections and
               general communication strategies.

               Boss  encourages  the  client  representative  to  attend  all  nominated  meetings  so  that  they  are  fully
               informed throughout all stages of project. This ensures that should there be any issues or delays they are
               communicated, identified and dealt with promptly to ensure a smooth delivery of the project.