Page 12 - Boss Projects Group Submission - Leidos Mezzanine Refit
P. 12

PRELIMINARY PROGRAM & SUPPORTING METHODOLOGY


               Program Millstones:

               Please prefer to the submission attachments for the Preliminary Construction Program REV A for further
               details. This project program details the Pre-Construction, Construction and Post Construction
               timeframes based on the project scope fo works. We believe that the project milstones nominated in
               the Statement of Works are acheivable based on commencement on site of 16 October 2016.



                                        Item                                       Milestone Date
                                    Tender Close                                  5pm, 19July 2017

                                  Award of Contract                                10 August 2017

                                  Possession of Site                              16 October 2017
                        Date for Practical Completion / Handover                 22 November 2017



               Task Appreciation

               We understand that the proposed project is to be undertaken during hours with all noisy or disruptive
               works to be undertaken out of hours to minimise disruption to tenants on either side.

               We are aware that Leidos need to continue normal business operations in the building and their daily
               operations should not be affected or interrupted by the fitout works. If successful Boss Projects Group will
               ensure that all building procedures and processes will be adhered to and our extensive experience in
               working within public spaces and occupied buildings will ensure the general public and occupants will not
               be hindered or impeded in any way.

               In brief, the works will include:

                       Construction of 4 off new office Executive Office,
                       Construction of 2 off Visitors Offices
                       24/25 off Open plan office work points to include workstations, screens, mobile pedestals, task
                       chairs and reticulated services.
                       Modifications to the existing kitchen unit in the breakout space to allow for the increased staff
                       numbers
                       Modifications to the existing mechanical, fire, electrical and communication services to suit the
                       new office and open plane space.
                       Modifications to the existing entry door to allow for automatic disabled access


               Design Development

               If successful, and following the award of the contract, Boss will arrange a start up meeting with Leidos to
               confirm design requirements and commence design concepts.



                                                                                                  12 | P a g e