Page 16 - Boss Projects Group Submission - Leidos Mezzanine Refit
P. 16
Boss believes that open and transparent communication between all parties is paramount in achieving
the project requirements, achieving the practical completion date and delivering a high quality project to
the satisfaction of Leidos.
Boss has developed a communications matrix for the project and believes this will provide all parties with
a guideline on what types of communication is available throughout the course of the project.
Communication Type Frequency Format Participants/ Deliverable
Distribution
PCG Reports Fortnightly On site and issue soft Project Manager, Project PCG Report
copy via email Officer
Program Project Team to Review On site and issue soft Project Manager, Site Updated weekly
weekly and issue copy via email Manager, Project Officer,
updated status monthly Sub-contractors
Quality & Test Records As Works progress Email Project Manager, Site Throughout the lifecycle of
Manager, Project Officer the project
Work as executed End of Project Soft copy and hard copies Project Manager, Project At Practical Completion
documents and O&M made available in person Officer
Manuals
Site Inspections As required In Person Project Manager, Project
Officer, Design Team
16 | P a g e