Page 13 - Boss Projects Group Submission - Leidos Mezzanine Refit
P. 13

On completion of these concept documents, Boss will issue to Leidos for review and comment. Changes
               will be made accordingly and these documents will be re-submitted for approval.

               Following Leidos approval, Boss will prepare and submit these documents to the Private Certifier for the
               Building Approval process to commence.

               Boss  will  manage  all  correspondence  with  the  Private  certifier  and  ACTPLA  to  achieve  the  building
               commence commencement notice and the subsequent Certificate of Occupancy and Use on completion.

               Subcontractor Engagement and Mobilisation

               Boss  will  engage  the  trade  subcontractors  to  deliver  the  design  brief  based  on  the  approved  design
               documents. Boss will ensure that all subcontractor comply with the documents and also comply with Boss
               Safety and legislative requirements.

               During the mobilisation period prior to commencement on site the following activities will take place:

                       Engagement of subcontractors
                       Ordering of materials and leadtime items inclusive of furniture and workstations
                       Preparation of Boss Project Safety plan and subcontractor SWMS
                       Preparation of Dilapidation Report
                       Establishment of the Boss Construction Site
                       Building and Project Inductions


               Site Establishment and Preliminaries

               Before commencement on site Boss Projects Group will carry out a fully detailed dilapidation report which
               will be submitted to Leidos for review.

               A project specific Project Management Plan along with Risk Registers and Project Specific Forms will be
               prepared and submitted to Leidos and Sub contractor SWMS will be collected and signed off prior to works
               commencing on site.

               Boss will ensure that construction lighting and temporary power services are adequate for the works.
               We will ensure that the Fit out is progressively cleaned, included daily tools down period of prior to
               completing each afternoon and subcontractor’s daily cleaning.

               Setout

               Prior to any construction commencing we will ensure that a detailed set out is carried out. The set out
               will be used to determine pre manufactured items such as mechanical ductworks etc.

               Once the site setout is signed off, the following items can be ordered / manufactured / completed:

                       Glass, to the new partitions
                       Window Blinds to the perimeter
                       Replacement kitchen joinery




                                                                                                  13 | P a g e