Page 9 - Boss Projects Group Submission - Leidos Mezzanine Refit
P. 9
▪ We have made an allowance for the cost of a building permit, private certification and statutory
fees.
▪ We have made no allowance for the removal of asbestos or other hazardous materials.
▪ We have made no allowed for works due to latent conditions.
▪ We have made no allowance for the separation of power or the installation of new metering.
▪ We have made no allowance for the upgrading of existing services mains.
▪ We have only allowed to makegood works affected by demolition works in the works area.
▪ We have made no allowance for temporary power or water and have assumed toilet/washing
facilities are available on site.
PRICING BREAKUP
ITEM DESCRIPTION Value ($)
1 DEMOLITION, PARTITIONS, DOORS & CEILINGS $40,200.00
2 FLOOR FINISHES $ 3,600.00
3 WORKSTATIONS, FURNITURE, JOINERY & KITCHEN SERVICES $77,700.00
4 PAINTING $ 2,980.00
5 ELECTRICAL, COMMUNICATION & SECURITY SERVICES $21,140.00
6 MECHANICAL & FIRE SERVICES $ 9,500.00
7 MISC- BLINDS, CLEANING, BWICS, BA, DESIGN $16,100.00
TRADE TOTAL $171,220.00
PRELIMINARIES, OVERHEADS & PROFIT $ 26,608.00
TOTAL EXCLUDING GST $197,828.00
Please contact the undersigned if you have any questions regarding this quotation or require further
information.
Yours sincerely
BOSS CONSTRUCTIONS (ACT) PTY LIMITED
BEN SAUNDERS
OPERATIONS MANAGER
9 | P a g e