Appendix I—Program and Portfolio Management Process Models


                Program Cost Budgeting
                Establish cost budgets for individual projects and program.


                                                  Program Cost Budgeting
                         Inputs          Tools & Techniques        Controls              Outputs
                   .1 Cost estimates    .1  Cost budgeting tools and    .1  Managerial peer review    .1 Cost baseline
                   .2 WBS                 techniques             on exception basis
                   .3 Program schedule                        .2 Executive oversight
                   .4  Risk management plan












                Program Quality Planning


                Identifying which standards are relevant to the Program, and determining
                how to satisfy them.


                                                 Program Quality Planning

                         Inputs          Tools & Techniques        Controls              Outputs
                   .1 Quality policy    .1 Benefit/cost analysis   .1 Checklists    .1 Quality management plan
                   .2 Scope statement   .2 Benchmarking                             .2 Operational definitions
                   .3 Product description   .3 Flowcharting                         .3 Checklists
                   .4  Standards and regulations   .4  Design of experiments        .4  Inputs to other processes
                   .5  Other process outputs  .5  Program Cost of Quality









































                ©2003 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA      135