Page 155 - Organizational Project Management
P. 155

Appendix I—Program and Portfolio Management Process Models


                Program Quantitative Risk Analysis
                Measuring the probability and consequences of risks and estimating their
                implications for Program objectives.


                                             Program Quantitative Risk Analysis

                         Inputs          Tools & Techniques        Controls              Outputs
                   .1  Risk Management plan   .1 Interviewing   .1  Management oversight    .1  Prioritized list of quantified
                   .2 Identified risks   .2 Sensitivity analysis   .2 Program Audits  risks
                   .3  List of prioritized risks   .3  Decision tree analysis       .2  Probabilistic analysis of
                   .4  List of additional analysis    .4 Simulation                   the Program
                     and management                                                 .3  Probability of achieving
                   .5 Historical information                                           the cost and time
                   .6 Expert judgment                                                 objectives
                   .7  Other planning outputs                                       .4  Trends in quantitative
                                                                                       risk analysis results











                Program Risk Response Planning
                Developing procedures and techniques to enhance opportunities and reduce
                threats to the Program’s objectives. The tools include avoidance, mitiga-
                tion, transference, and acceptance.


                                              Program Risk Response Planning

                         Inputs          Tools & Techniques        Controls              Outputs
                   .1  Risk management plan   .1 Avoidance    .1  Risk Response Plan Review  .1  Risk Response plan
                   .2  List of prioritized risks   .2 Transference                  .2 Residual risks
                   .3  Risk ranking of the   .3 Mitigation                          .3 Secondary risks
                     Program            .4 Acceptance                               .4 Contractual agreements
                   .4  Prioritized list of quantified                               .5 Contingency reserve
                     risks                                                            amounts needed
                   .5  Probabilistic analysis of the                                .6  Inputs to other processes
                     Program                                                        .7  Inputs to a revised
                   .6  Probability of achieving the                                   Program plan
                      cost and time objectives
                   .7  List of potential responses
                   .8 Risk threshold





























                ©2003 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA      139