GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



               2.17.9  Circuit Wiring


                         Wiring shall be carried out using FP200 cables as described elsewhere in this specification.
                         Where cables run parallel to cable trays, they may be installed on the tray.

                         The whole of the cable installation shall comply with clause 17 of BS 5839 : Part 1

               2.17.10 Inspection, Testing and Commissioning

                         The whole of the installation shall be inspected, tested and commissioned in accordance
                         with clause 26 of BS 5839 : Part 1 and as further described.

                         The Electrical Contractor shall employ the fire alarm equipment manufacturer to set to
                         work, test and commission the completed system.
                         Commissioning shall be carried out in accordance with clause 26.5 of BS5839 : Part 1,

                         which shall include: -
                         a.   An audibility test of the alarm devices. Audibility level readings shall be taken in each
                              room using an instrument complying with BS 5969, type 2 with ‘A’ weighting. Any
                              sound pressure levels found to be lower than that required be clause 9.4.1 of BS
                              5839 : Part 1 shall be reported in writing to the Engineer.
                         b.  All trigger devices i.e. manual call points, heat detectors and smoke detectors shall
                              be tested for correct operation.
                         c.   A mains failure test shall be carried out to verify the standby battery system complies
                              with the requirements of this Specification.


                         Prior to commissioning the Electrical Contractor shall provide a certificate of installation
                         and commissioning of the system (See appendix B and C of BS 5839: Part 1) to the
                         Engineer. It should be noted that a Practical Completion Certificate will not be issued until
                         this installation and commissioning certificate has been received and the installation and
                         commissioning certificate will not be accepted unless it is accompanied included within
                         the Record Drawings and User Manuals and the system Log Book (see appendix D of BS
                         5839 : Part 1).
                         On completion of the installers commissioning the Electrical Contractor will notify the
                         Project Manager that the system is ready for testing by McDonalds specialist fire alarm
                         maintenance Contractor.

               2.18  EARTHING

                         A full system of earthing shall be provided by the Electrical Contractor. The Electricity
                         Board will normally provide an earthing connection at their cut-out from their network,
                         which shall be of the TN-C-S type. The Electrical Contractor shall ascertain the earthing
                         arrangements to be provided by the Electricity Board and any departures from the above