Page 99 - Bernardon Response to RFP-Chestnut Run Campus Master Plan
P. 99

AVENUE NORTH CHANNEL RESTORATION
                Channel Erosion Caused by Degraded Stormwater Outfall Pipe

                As part of a Land Development Proposal, the property Owner and Developer were required   LOCATION
                by New Castle County to assess and correct severe ongoing erosion within an existing   FAIRFAX, NEW CASTLE
                drainage channel as part of the 80-acre Avenue North mixed-use redevelopment of the   COUNTY, DE
                former AstraZeneca campus.  Landmark was charged with developing a solution.   YEAR COMPLETED
                This erosion was a result of long-term uncontrolled discharges during storm events from an   2019 Recordation
                existing 48-inch concrete pipe outlet. The existing underground system piped stormwater   2020 Parking Garage
                runoff from a ±60-acre drainage area consisting mainly of rooftops, lawns and paved   2020 Channel
                surfaces. These pipes converged into the 48-inch concrete pipe that discharged up to 120   Restoration
                cubic feet per second of stormwater directly into the existing earthen channel which
                scoured the banks and undercut large trees over time. This 210-foot drainage channel   SIZE
                flowed southward through a forested area and exited the site through four 12” pipes   1,860,000 SF
                randomly embedded in a concrete structure beneath a steel security fence. The concrete   960,000 SF office*
                structure was severely undercut and eroded from historical stormwater surges and the   (*100,000 SF new)
                small pipes easily became clogged with debris. Beyond the concrete structure, the   200,000 retail
                stormwater entered the existing drainage system associated with Powder Mill Road.   175,000 hotel
                                                                                              335 apartment units
                The project involved hydraulic grade line and stormwater volume analyses, site-specific   7-story parking garage
                design of concrete culvert to control site outflow, a two-tiered gabion basket weir/scour-
                hole structure to control in-flow, and two J-hook rock vanes in the channel bed to direct   ACRES
                water flow. Our bank restoration design reduced the steep slopes of the existing channel   80
                and protected them with rip-rap, geotextile fabric, live stakes, native plant landscape design   COST
                and seeding for long-term stabilization.
                                                                                              $400,000,000+ Total
                The Delaware Department of Natural Resources & Environmental Control Wetlands Section   Project Construction
                issued a Subaqueous Lands Permit and the U.S. Army Corps of Engineers granted a   $250,000+ Restoration
                Nationwide Permit 13 for this project in February 2020. Compensatory mitigation was
                waived by both agencies as the benefits of the project (stemming erosion and improving
                downstream water quality) outweighed the minor impacts to jurisdictional waters.
                Construction of the new outfall structures and restoration of the channel was completed in
                August 2020.

                Landmark performed all planning, topographic surveying, wetland and forest stand
                delineations, environmental permitting, civil engineering, landscape design, construction
                stakeout and as-built surveys required for the successful and timely completion of project.
   94   95   96   97   98   99   100   101   102   103   104