the August Graypvine update. The finished goods         The site team at Owens Corning raised $1,043
            warehouse and cooler space are enclosed and           to help a local family in Ft. Smith for Christmas. In
            substantially dried in. Structural framing, deck,     construction news, the warehouse is dried in and
            exterior IMP and roofing are in place for the         about 95% complete. Steel for the manufacturing
            packaging and production areas. Floor coatings        building is being erected and the building is targeting
            have been installed in the kitchen pits. Interior walls   a dry in date of February 18, 2022. The walls for the
            and protective curbs are being installed. Walkable    30’ deep basement are completed and backfilled,
            ceiling panels will begin soon. MEP overhead          and work on the cap has commenced.
            work continues. Centria siding panels are being         As 2021 came to a close, Project Panda had just
            installed on the office. Asphalt paving base course   celebrated its one-year anniversary. This time last
            is complete. Surface course will be placed this       year, underground utilities and foundations were
            spring. Planned shutdown work for utility and         going in and steel erection was about to start. Now,
            ingredient tie-ins was successfully executed leading   the project is well into early access turnovers and
      4     up to and including the Thanksgiving holiday.         the installation of process conveyors and spirals
                                                                  are underway. To-date, Gray has finished closing in
            Process and controls engineering and design are
            nearly complete, with particular emphasis on RFI      the building, ensured exterior paving and sidewalks
            responses, procurement and delivery coordination.     are in good shape, and completed the installation
            Long-lead equipment has been purchased                and start-up of roof top units – just in time for our
            with initial production equipment deliveries now      second Detroit winter. In partnership with Hillwood
            occurring. The project schedule has been revised to   and Sterling Group, the Panda project team and
            reflect a September 2022 completion.                  its subcontractors helped in a revitalizing effort