WORKING DRAWING


           After analysis of all plans, elevation, sections and 3d I started to working in
           working drawing before starting the drawing the check list is to be prepared .first, I
           learned the standard working format of our office and started drawing starting with
           adding plasteline of 15mm thick and tile line of 10mm thick.
           Then interior dimension is provided similarly exterior dimension is provided in three
           layer one is detailed dim ,another is from columns center to center and last one is
           total dimension .







































































           5          Note: Fore more detail prefer annex drawing page no. (1-55)