Page 43 - RotF - Electrical Specification_Neat
P. 43

GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



               1.2.45  Protection Against Legionnaires Disease


                         Adequate protection to all  water installations should be incorporated by the Electrical
                         Contractor  to cover the event of Legionnaires Disease as recommended by the CIBSE
                         Technical Memorandum TM13 "Minimising the Risk of Legionnaires Disease" - 1991, and
                         guidance note GN03 1993  -  Legionnaires, interpretation of HSC Approved Code of
                         Practice.
               1.2.46  Subsequent Failure of The Contract Works


                         If the Contract Works are maintained by the Employer in accordance with the Contractor's
                         maintenance manual and directives and the Contract Works subsequently fail within the
                         period of defects liability then the Electrical Contractor is to identify the reason for failure
                         whether it is latent or otherwise.
                         The Electrical Contractor is to rectify the defect within a reasonable time agreed with the
                         Client and or store manager together with making good all damage resulting from defect
                         at no cost to the Client providing that the Electrical Contractor is not required to correct
                         any defect due to normal wear and operation.

                         The Electrical Contractor shall be required to provide a fully detailed written report to the
                         Project Manager of each and every such defect together with the remedial works
                         undertaken within seven days of such remedial works.

               1.2.47  Mechanical

                         The Electrical Contractor is to supply, install and provide 'as installed' record drawings and
                         operation & maintenance manuals, commission and demonstrate as applicable, all the
                         necessary materials, components and equipment to form a complete working installation
                         at the premises in accordance with all relevant British and European Standards. The
                         completed installation, new and existing services adapted as part of the contract are to be
                         fully in accordance with all relevant BS/EN Regulations and local authority requirements.

                         The Electrical Contractor is to be responsible for identifying and making suitable provision
                         for, the mechanical characteristics of all materials, equipment and components as
                         specified or having an impact upon the design or performance of the mechanical services
                         installation.

                         The Electrical Contractor is to be responsible for identifying at an early stage; the delivery
                         period associated with all equipment and is to satisfy himself that these can be procured
                         within the constraints of the construction programme, without adverse effect on the
                         project.

                         Should the Electrical Contractor identify any potential problems these are to be reported
                         as soon as is practicably possible.



                                                      McDonalds Restaurants Ltd

                                                                21
   38   39   40   41   42   43   44   45   46   47   48