GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



                         Should the Contract Works, or sections thereof, fail the witness test or not be available for
                         witness testing at the appointed time resulting in an abortive visit by the Project Manager,
                         the Electrical Contractor may become liable to a charge for the Project Manager to re-
                         attend the re-testing or re commissioning.

               1.2.33  Timely Submission of Record Documents

                         The Project Quantity Surveyor shall recommend to the PM that a minimum sum to be
                         determined by the PM is withheld from the Electrical Contractors final account pending
                         submission of approved record documentation as defined elsewhere in this document.

                         Should the  Electrical Contractor  fail to provide the record documents within the time
                         specified  under written notice, the Project Manager is to instruct the works to be
                         executed by other competent bodies and the actual costs of this instruction shall be
                         deducted from the contract sum.

               1.2.34  Drawn and Other Information

                         The Project Manager shall require 10 working days from receipt of drawings to
                         examine/comment and, if necessary, a further 5 working days from receipt to re-examine,
                         where the initial issue is not acceptable. These time periods are to be included within the
                         Electrical Contractors programme to  ensure timely issue of information.

                           1.  Provide calculations where applicable.
                           2.  .Provide final sets of Operation and Maintenance manuals in accordance with the
                               main contract requirements (but shall be a minimum of 2 hard copies) inclusive of
                               drawings and CD-ROM of manual and drawings (AUTOCAD DWGs and PDFs).

               1.2.35  Timely Completion of Outstanding Works


                         The  Electrical Contractor  shall be provided by the Project Manager upon Practical
                         completion with a list of incomplete and unacceptable works. The Electrical Contractor
                         shall remedy the incomplete or unacceptable works within a maximum of one week
                         unless stated elsewhere.
                         The Electrical Contractor is to produce a written schedule of those items, on the Project
                         Managers list of incomplete and unacceptable works that he is unable to remedy within
                         the written period of notice.

                         The incomplete and unacceptable works shall be valued by the Project Manager with a
                         sum of money withheld from the Electrical Contractors final account pending remedy of
                         the incomplete and unacceptable works.

                         Should the  Electrical Contractor fail to remedy the defects within the specified time
                         period issued under written notice, the Project Manager is to instruct the works to be
                         executed by other competent bodies and the cost of instruction shall be deducted from or
                         added to the retained sum.