Page 33 - RotF - Electrical Specification_Neat
P. 33

GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



                         installations where all or part of the systems has been effected/altered by the works
                         required by these employers’ requirements:

                                                         th
                           1.  The latest IET Regulations (17  Edition)
                           2.  BSRIA Application Handbooks
                           3.  BSRIA Application Guides
                           4.  BSRIA Technical Memorandums
                           5.  CIBSE Commissioning Codes

                         During the progress of the work and on completion the Electrical Contractor is to carry
                         out such tests and provide such apparatus, instruments and materials as the Employers
                         Agent may consider necessary and as may be reasonably demanded to prove compliance
                         with the requirements of this specification.

                         The Electrical Contractor is to carry out all commissioning and tests necessary and submit
                         completed record sheets, prior to any acceptance witness tests requested by the Project
                         Manager.

                         The whole of the electrical installation is to be tested at completion in the manner
                         prescribed in the latest IET Regulations.
                         Within 4 days following the inspection and testing of part or the whole of the electrical
                         installation the Electrical Contractor is to forward inspection and completion certificates

                         as described in the latest IET Regulations.
                         The mechanical installation is to be tested and commissioned at completion in the
                         manner prescribed in the CIBSE Commissioning Codes and BSRIA Applicat ion Guides.

                         Where the work requires phased hand over and completion, the Electrical Contractor is to
                         allow for undertaking phased commissioning of the works.  The Electrical Contractor  is to
                         allow for return to all previously completed phases upon the comp letion of the final phase
                         to undertake an overall re commission and balance of all systems.

                         The Electrical Contractor  is to supply at his own expense all fuel, instruments, meters,
                         cables, rods, lamps and resistances, etc., required to carry out tests. These instruments
                         are to remain the property of the Electrical Contractor who is to accept full responsibility
                         for their accuracy and safety.

                         The commissioning is to be carried out to a programme agreed with the Main Contractor.
                         The  Electrical Contractor  is to allow all necessary costs in connection with the
                         commissioning to co-ordinate his works and provide the necessary flow data and
                         information.

                         Any witnessing of commissioning by the Project Manager is to be by prior appointment
                         with at least five working days notice.  Additional spot checking may be required by the
                         Project Manager when the Electrical Contractor has confirmed that all systems have been



                                                      McDonalds Restaurants Ltd

                                                                11
   28   29   30   31   32   33   34   35   36   37   38