GENERAL ELECTRICAL SPECIFICATION
Version 2014-2
installations where all or part of the systems has been effected/altered by the works
required by these employers’ requirements:
th
1. The latest IET Regulations (17 Edition)
2. BSRIA Application Handbooks
3. BSRIA Application Guides
4. BSRIA Technical Memorandums
5. CIBSE Commissioning Codes
During the progress of the work and on completion the Electrical Contractor is to carry
out such tests and provide such apparatus, instruments and materials as the Employers
Agent may consider necessary and as may be reasonably demanded to prove compliance
with the requirements of this specification.
The Electrical Contractor is to carry out all commissioning and tests necessary and submit
completed record sheets, prior to any acceptance witness tests requested by the Project
Manager.
The whole of the electrical installation is to be tested at completion in the manner
prescribed in the latest IET Regulations.
Within 4 days following the inspection and testing of part or the whole of the electrical
installation the Electrical Contractor is to forward inspection and completion certificates
as described in the latest IET Regulations.
The mechanical installation is to be tested and commissioned at completion in the
manner prescribed in the CIBSE Commissioning Codes and BSRIA Applicat ion Guides.
Where the work requires phased hand over and completion, the Electrical Contractor is to
allow for undertaking phased commissioning of the works. The Electrical Contractor is to
allow for return to all previously completed phases upon the comp letion of the final phase
to undertake an overall re commission and balance of all systems.
The Electrical Contractor is to supply at his own expense all fuel, instruments, meters,
cables, rods, lamps and resistances, etc., required to carry out tests. These instruments
are to remain the property of the Electrical Contractor who is to accept full responsibility
for their accuracy and safety.
The commissioning is to be carried out to a programme agreed with the Main Contractor.
The Electrical Contractor is to allow all necessary costs in connection with the
commissioning to co-ordinate his works and provide the necessary flow data and
information.
Any witnessing of commissioning by the Project Manager is to be by prior appointment
with at least five working days notice. Additional spot checking may be required by the
Project Manager when the Electrical Contractor has confirmed that all systems have been