Page 32 - RotF - Electrical Specification_Neat
P. 32
GENERAL ELECTRICAL SPECIFICATION
Version 2014-2
3. Operation and Maintenance manuals, instruction charts, diagrams, record drawings
etc. have been submitted, approved and supplied.
4. A complete demonstration of every service has been carried out with full functional
operational controls tested and demonstrated and instructions given to Client's
staff to show proper working.
1.2.16 British Standard Specifications
All equipment, materials and workmanship are to comply fully with the requirements of
the relevant British Standard and/or its European equivalent (BS EN ISO)
1.2.17 Specialist Trade Attendance on Plant and Equipment
The Electrical Contractor is to arrange and make payment for specialist tradesmen to visit
site, adjust and put into working order all items of specialised plant and equipment
supplied under the Contract.
1.2.18 Cleaning Down Equipment
On completion of the works or section of the works any new item and/or existing item of
equipment that has been soiled (by the Contractor or his Sub-Contractors) are to be
thoroughly cleaned internally and externally and where applicable polished by the
Contractor.
1.2.19 Maintenance of New Equipment
All items of equipment whether put into operation before the completion of the Contract
or not must be maintained in perfect order by the Electrical Contractor until the Practical
Completion of the installation or until an agreed section of the installation is officially
handed over to the Client.
1.2.20 Discrepancies
Any apparent discrepancies within the Employers Requirements are to be noted at the
time of tendering. No claim for extra costs shall be considered in respect of any item
described in the Employers Requirements.
1.2.21 Testing and Commissioning Of the Works
The Electrical Contractor is to undertake a pre commissioning exercise of the installations
to prove correct operation of lighting control and other interlocked systems, air and water
flow rates and temperatures and water condition.
The Electrical Contractor is to carry out all necessary commissioning and testing, both as
the installation proceeds and on completion to ensure the correctness of the installation
and its compliance with the following (where no suitable code exists for commissioning an
item of plant, the manufacturer's recommended method of commissioning should be
used). The Electrical Contractor shall be required to re commission the entire system
McDonalds Restaurants Ltd
10