Page 35 - RotF - Electrical Specification_Neat
P. 35

GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



                         In the event of the  Electrical Contractor nominating an alternative manufacturer for
                         specified equipment, he is to be responsible for ensuring that it is equal or better  in
                         performance to the original, and that it is dimensionally suitable for the installation. Any
                         additional costs arising out of the necessity of re-planning, relocating or refitting
                         equipment due to the use of such alternative equipment is to be borne by the Electrical
                         Contractor.

               1.2.24  Defects

                         Prior to Practical Completion and when the Electrical Contractor has satisfied himself that
                         all work is complete and defect free in accordance with the Employers requirements, the
                         Electrical Contractor is to offer the works to the Project Manager for inspection. The
                         Project Manager shall prepare a Schedule of Defects and formally issue them through the
                         Electrical Contractor for action by the Electrical Contractor. The Electrical Contractor is to
                         inform all parties when he considers all remedial works have been complete.

                         Concealed or buried work is to be inspected and tested in the presence of the Project
                         Manager before any permanent covering is applied. The Electrical Contractor is to give
                         due notice, , to the Project Manager when the work is ready for inspection and the
                         Project Manager shall, without reasonable delay, carry out his inspection and/or witness
                         the tests unless he informs the Electrical Contractor in writing that he considers the tests
                         unnecessary.

                         In no instance is concealed or buried work to be covered without being fully tested and
                         documented by the Electrical Contractor.

                         In the event of the Electrical Contractor failing to complete all defect works to any area
                         within the desired period to the satisfaction of the Project Manager, the Client may
                         instruct the Project Manager to achieve the desired completion(s) with whatever
                         assistance is deemed necessary.

                         The cost of such assistance inclusive of the Project Manager's costs for each and every
                         occasion shall be deducted from the Electrical Contractor's payments.
               1.2.25  Schedule of Rates


                         The Contractor is to, as set out in the main contract documents, submit a fully detailed
                         Schedule of Rates inclusive of all material and labour rates and indicating all associated
                         overheads and profits.
                         The Schedule of Rates are to show in detail the quantities, process and extensions used in
                         the calculation of the Tender Prices and the Electrical Contractor is to accept
                         responsibility for the accuracy of any quantities and extensions contained therein and the
                         Schedule are to balance with each priced item of the  Electrical Contractors Tender
                         summary.



                                                      McDonalds Restaurants Ltd

                                                                13
   30   31   32   33   34   35   36   37   38   39   40