GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



               1.2.39  Sub-Letting


                         The Electrical Contractor is to only be permitted to use those Specialist sub-Contractors
                         who were previously named on the tender summary unless the express permission of the
                         PM is sought and received in writing.
               1.2.40  Method Statements


                         The  Electrical Contractor  is to provide method statements of all working procedures
                         which are to be submitted to the PM for comments at least 1 week before work is
                         programmed to be carried out. The Electrical Contractor must allow at least 5 days for
                         comments to be returned and must include for any actions from the comments. Method
                         statements shall need to incorporate all other Electrical Contractor requirements.
               1.2.41  Existing Services


                         Before isolating or connecting into any existing services the approval of the PM/User is to
                         be obtained.
                         The period of notice required before such isolation or connection takes place is to be
                         ascertained from the PM/User. Once the works associated with the existing services has
                         commenced and the services interrupted, work must proceed without pause until the
                         services are restored.

                         The Electrical Contractor is to ascertain from the PM/User which, if any, "permit to work"
                         systems are in operation, and is to follow in total all such systems.

                         The location of existing services within the site is not accurately known and the Electrical
                         Contractor  is to be responsible for establishing the precise location of all services and
                         drains within the area of the work to be executed. The Electrical Contractor is to protect,
                         maintain, uphold and reinstate any damage caused by water pipes, electricity, voice and
                         data cables, drains and the like exposed during the execution of the works.

                         Where existing or part complete services need to be cleaned down and re-filled, the
                         Electrical Contractor is to allow for any necessary dosing or water treatment to match the
                         existing water qualities.

               1.2.42  Details of Material, Goods, Plant & Equipment Delivered To Site

                         The  Electrical Contractor shall retain records on site for all goods, materials, plant or
                         equipment delivered to site during the course of the project.

               1.2.43  Protection & Cleaning Of Materials & Contract Works

                         The Electrical Contractor is to include in his Tender for taking all necessary precautions to
                         protect materials, goods, plant and equipment from damage and theft during the
                         execution of the contract works and is to be liable for such damage and theft.