Page 311 - Area_VI_Parameter_A
P. 311
28
Section 8. Monitoring and Evaluation of Extension Projects. To ensure
efficient and effective project implementation, monitoring and evaluation shall be
conducted by the Monitoring and Evaluation Division with the identified technical
expert.
a. Progress Reports. All project proponents are required to submit two (2) hard
copies and electronic copy of their semi-annual and annual reports duly
endorsed by the Campus/College Dean or Unit Head.
b. On-site/Field Monitoring. If necessary, on-site or field monitoring shall be
conducted to validate the progress reports submitted by the proponent. The
schedule shall be set by the Extension M&E Division.
c. Semi-Annual/Annual Review. Semi-annual review (for one year projects)
and annual review (for multi-year projects) are conducted to determine the
continuance or termination of an extension project. The number of reviews to
be conducted annually shall depend on the number of on-going projects.
Schedule of which shall be set by the Extension Center. Selected members of
Research and Extension Council and/or experts from other institutions shall be
invited as evaluators during the review.
During the review, proponents shall present the progress and plans for
the continuation of implementation of the project. Evaluators shall provide
their comments/suggestions/ recommendations on the progress report and
presentation. The M&E division shall document, integrate/consolidate the
given comments and suggestions. The same shall provide the proponents copy