Control of Industrial Major Accident Hazards (CIMAH) Report   Page       30
                                               Ranhill SAJ Sdn. Bhd.                    Revision      01
                            Part C: Information Relating to the Safety Management System  Date      Aug 2019



                No   Safety-Critical Equipment / Element             Standard               Checker
                                                              Manufacturer Standard
                 1   Automatic Shutdown System                                          Contractor
                                                              Performance Test Report

                 2   Overhead Crane                           Manufacturer Standard     Contractor


                 3   Emergency Wet Scrubber System            Manufacturer Standard     Contractor

                                          Table C.2.4.1: Safety Critical Equipment

               The objectives of the inspection and testing activity are to:
                   •  Ensure the safety and integrity of plant (equipment and piping systems); and
                   •  Ensure the design, repair or  modification  of pressure containing equipment
                       and piping systems  to meet company, design code and statutory
                       requirements, whereby maintaining the safety and integrity of the assets.
               The maintenance and inspection activity involves:
                   •  Functional test of the firefighting system;
                   •  Scheduled inspections of chlorine cylinders / drums; and
                   •  Test program for pressure relieving valves.


               C.2.4.1 Inspection and Testing Schedules

               Chlorine cylinders / drums shall be subjected to testing and inspection during and
               after  manufacturing  as to compliance with  the  applicable design standards.  This
               testing and inspection are conducted by the chlorine’s manufacturers via the yearly
               qualification and requalification test and subject to the acceptance by the approving
               authority such as DOSH. Besides the chlorine cylinders / drums, the storage facility
               has  an inspection and testing program  to ensure  the integrity  of the plant  and
               equipment are maintained.

               The Inspection, test and maintenance program performed on plant and equipment is
               documented and takes into account:
                   •  Recognized and accepted good engineering practices and procedures for the
                       planned inspection and maintenance of plant and equipment;
                   •  Frequency determined by:

                       -  Manufacturers specifications and recommendations;
                       -  Good engineering practice;
                       -  Operating experience;
                       -  Hazard analyses and risk assessments;

                       -  Maintenance and reliability experience; and
                       -  Regulatory requirements and industry codes.