Control of Industrial Major Accident Hazards (CIMAH) Report   Page       31
                                               Ranhill SAJ Sdn. Bhd.                    Revision      01
                            Part C: Information Relating to the Safety Management System  Date      Aug 2019


                   •  Information requirements that include equipment identification, description of
                       the inspection or test, the condition of the equipment and the results;
                   •  Records of inspection and testing results, repairs or alterations;
                   •  Technical knowledge required; and
                   •  Mandatory testing of pressure vessels and equipment.
               The inspection and testing program is regularly reviewed for appropriateness, design
               limits,  accuracy and have  a valid calibration certificate.  The system includes
               independent inspection testing where  necessary to verify the adequacy of the
               inspection and testing program, the integrity of processes, plant, and equipment.

               All pressure testing is carried out  under  strict Permit  to  Work conditions and
               performed by the  approved and competent personnel to  carry out the task.  Test
               areas are isolated and all valves and instruments are identified and isolated using
               the isolation procedure.

               C.2.4.2 Risk-Based Inspection

               A risk-based inspection (RBI) strategy is  used  for piping systems  and pressure
               containing equipment items. The RBI concept is based on a thorough understanding
               of the  processes and operating conditions together with the  maintenance and
               inspection  history of the  equipment and piping systems.  The inspection programs
               and  schedules are defined  based  on detailed studies related to the operational
               aspects of the equipment and piping systems.
               The Company has identified inspection frequency based on the associated risk of
               failure and criticality of the said equipment when on demand.

               C.2.4.3 Pressure Relieving Valves Test

               In line with codes and standards, all pressure relief valves are subject to inspection,
               overhaul and calibration. All tests are witnessed and approved  by the Inspector
               before the valve is allowed to be re-installed at the plant.


               C.2.4.4 Maintenance

               The maintenance regime of the plant has the following objectives:
                    •   To preserve the investment in the existing facilities and meet their functional
                        requirements; and
                    •   To  maximize integrity, reliability, availability, and utilization of  plant and
                        equipment.