            INSTALLATION AND STARTUP


            Chapter 4 Frame and Carriage Assembly


            Carriage Placement

            You are now ready to place the carriage onto the rails. The Carriage Assembly arrives on the site
            secured to a shipping frame. When lifting it into place the forks can be inserted from either side as
            shown below.
            Note:  If you have fork extensions, the Carriage may also be lifted form the exit side of the shipping frame.



                                                                                       Approved
                                                                                       Lifting
                                                                                       Locations



                            Shipping Frame

                                                  CAUTION


                         Be sure to clamp the forks to the shipping frame before lifting.

            1)  From the entrance end, maneuver the Carriage Assembly into the bay on one of the forklifts and
               move to the position between the Rail Travel Stop and the Head Beam.
            2)  If the rail spacing was set to the 92-1/4’’ distance, then proceed immediately to the next step
               (Step 3). If the rail spacing was set to the 100’’ distance, proceed to step 4.
            3)  92-1/4’’ Rail Spacing: Pull the Carriage up to just in front of the rails. Have someone on each
               side of the machine to check clearance and slowly drive the machine onto the rails. Move directly
               to step 5.
                   Note:  There is 1/8’’ of clearance between the pods and the rails, keep this in mind when loading
                          the carriage onto the rails.
            4)  100” Rail Spacing: From the predetermined end, maneuver the Carriage into the bay on one of
               the forklifts and move to the position between the end of the rail and the Head Beam as shown
               below.

                                 Entrance                                          Exit