INSTALLATION & STARTUP
Chapter 6 Frame and Carriage Assembly
Frame Assembly (Hybrid)
Leveling the Frame
1) Place a level on each of the expansion rails at their center and a level on the opposite Crossbeam, also at its
center. Level the frame in both directions and secure the remaining 2 legs into place.
Place levels where the
dotted circles are
Note: It may be necessary to use field supplied shims under the legs (due to a sloping floor)
to proper level the system.
At this point with the legs are resting on the floor, both Crossbeams and expansion rails should be level.
2) Once the whole system is level and attached to the wall verify that the center of the head beam is lined up
with the center line of the doors If its not, loosen the Wall Mount Clamps and adjust them until the centers are
in line. Once they are, tighten everything down except the driver side rail which will remain loose until the
carriage is placed onto the rails.
3) To assist in the installation process later, drop a plumb bob from the center of the entrance and exit cross-
beam as shown below and mark the floor. Once marked, draw a reference line the width of the bay also
shown below.
Drop plumb-line
from exit surface of
entrance head
Drop plumb-line beam
from entrance
surface of entrance
head beam
Plumb-bob and line
on the floor
4) Fully tighten the fasteners on both Corner Clamps of the legs.