3) Locate the two 14” ground wires shown below.
4) Position one of them as shown below. Once the wire is contoured as shown below, place a mark in the holes
for drilling.
5) Drill and tap a 10-32 hole at both marks and then secure the ground wire into place.
6) Secure the other ground wire on the opposite side the same way.
7) Supply an electrical feed to the enclosure at the remaining cord grip and make the connections shown below.
Ground
120VAC
Ground to Supply Main
Crossbeam Electrical Feed
Neutral
Black Black
Wire Wire
Lead from Lead from
Heat Strip Heat Strip
White Wire White Wire