                      Chapter 6 Frame and Carriage Assembly



                      Optinal Rail Heat Installation Completion

                             3)  Locate the two 14” ground wires shown below.








                             4)  Position one of them as shown below. Once the wire is contoured as shown below, place a mark in the holes
                                 for drilling.























                             5)  Drill and tap a 10-32 hole at both marks and then secure the ground wire into place.

                             6)  Secure the other ground wire on the opposite side the same way.

                             7)  Supply an electrical feed to the enclosure at the remaining cord grip and make the connections shown below.







                                                                Ground
                                                                           120VAC
                                               Ground to                   Supply                 Main
                                              Crossbeam                                        Electrical Feed
                                                                            Neutral
                                                                 Black        Black
                                                                  Wire        Wire
                                   Lead from                                                         Lead from
                                    Heat Strip                                                       Heat Strip
                                                                  White Wire   White Wire








                       1MANUL290       Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681   6-31