Page 99 - Saber® Installation & Startup
P. 99
INSTALLATION & STARTUP
Chapter 6 Frame and Carriage Assembly
Connecting the Boom
5) When this is complete it will be necessary to attach the 3/4’’ x 55’’ long hydraulic hose from the accessory box to the end
of the short boom nipple and connect it to the nipple that sticks out of the high pressure valve on the machine. The loop
should look like the image below.
6) Once the pipe clamps are properly placed on the boom arms, all utility lines (for all system options; including triple foam
and lighting packages) should be routed thru the tie wraps neatly. See images below.
Note: Be sure to leave slack at each end of the boom and along the center hose to allow
proper flex of the lines.
High-Pressure Water Feed
1/2” Black Triple Foam Air Feed
3/8” Neutral Triple Foam Chemical Feed
Yellow Electrical Feed to Boom Junction Box
Black Electrical Feed to High-Pressure Valve
3/8” Neutral Triple Foam Chemical Feed
Gray Electrical Feed to Carriage Drive Motor Gray Electrical Feed to Dryer #1
Feed
Gray Electrical Feed to Butterfly Motor Black Electrical Feed to Arm Lights
Gray Electrical Feed to Dryer #2
Feed
1MANUL290 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 6-37