                Installation
                Tunnel Placement

                    5)  Once the driver side leg is square and plumb in all directions, drill the holes in the concrete and
                        use four (4) of the supplied 5/8” lag bolts to secure the driver side foot plate to the floor.


                       Note: Remember to verify where any underground heat or utilities run so you can be sure to not
                             drill into them with the hammer drill when making the lag holes.
                       Note: Do not hammer the lag bolts all the way down at this time, leave room to raise the foot plate
                             later if necessary.

















                                                                                                 Passenger Side














                        Driver Side







                                                                             5/8” Lag Bolts
                                                                              (4 per Leg)









                    6)  Next, for the passenger side foot plate, measure 139-½” from the OUTSIDE edge of the driver
                        side foot plate toward the passenger side of the tunnel and mark a line at this distance on the
                        floor.