Page 23 - H2AIR® Arch
P. 23
®
H2AIR ARCH
Installation
Attach Leg Assemblies to Head Beam Assembly
1) Locate and unwrap the driver and passenger side Leg Assemblies.
2) Retrieve the bolts and lock washers that were used to attach the Head Beam Assembly to the
Shipping Bracket.
3) With the H2AIR® Top Beam Assembly secured to the forklift raise it up so that the Leg
Assemblies can be attached.
4) Orient the legs on the driver and passenger side of the Head Beam with the manifolds facing the
center of the tunnel refer to the image below.
Head Beam
Passenger Side
Driver Side
LED Cable &
Water Hoses (2)
PS Leg Assembly
with Manifold
facing toward the
center of the tunnel
DS Leg Assembly
with Manifold
facing toward the
center of the tunnel
Manifold Nozzle Port
(8 per Leg)
1MANUL958 Belanger®, Inc. *PO BOX 5470 *Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 19